Answer :
Answer:
B. The aggregate plan
Explanation:
The aggregate plan is a study done typically 6-18 months before the production period that gives management an estimate of the quantity of materials and resources (labor, time, etc) that will be needed.
The aggregate plan is the correct answer to the following question.
Explanation:
Option "B" is the correct answer to the following question.
The aggregate plan is a research completed generally 6-18 months before even the period of production that knowledge on a particular things with an estimate of the amount of materials and equipment, as well as labour, time, and so on, that will be required.
Learn more:
https://brainly.com/question/20368207?referrer=searchResults
