Using the high-low method, find the variable cost per unit and total fixed costs. How do you find the variable cost and total fixed costs?

Answer :

jafransp

Answer:

See explanation below

Explanation:

Using the high-low method, we can find the variable cost per unit and total fixed costs.

The formula to find the variable cost per unit = [tex]\frac{Highest cost - Lowest cost}{highest number of units - lowest number of units}[/tex]

For example,

500 units = $4,000

600 units = $4,500

The variable cost per unit = [tex]\frac{4,500 - 4,000}{600 - 500}[/tex]

The variable cost per unit = $5

To determine the total fixed cost, we need to use the basic formula of total cost.

Total cost = fixed cost + variable cost

Total cost = fixed cost + variable cost per unit x quantity

In the above example,

we can choose either highest unit activity or least unit activity.

So, using least unit activity,

$4,000 = fixed cost + $5 x 500 units

or, $4,000 = fixed cost + $2,500

or, fixed cost = $1,500

Other Questions