Answer :
Answer:
Option D
This delay
Explanation:
The contract between Ruth and the contractor is assumed to be oral and since the contractor is supposed to complete a stage of the project when date for completion is over. Ruth can sue the contractor for the delay of the project. The contractor may consequently pay an interest for the delay of the project to Ruth.