Ruth owns Skyview, a complex under construction that will include commercial and residential suites, and a parking garage. She allows Town Contracting, the contractor, to complete a stage of the project late. Thiswaives Ruth's right to sue for​ Select one: a. ​none of the choices. b. ​any subsequent breaches. c. ​any past breaches. d. ​this delay.

Answer :

opudodennis

Answer:

Option D

This delay

Explanation:

The contract between Ruth and the contractor is assumed to be oral and since the contractor is supposed to complete a stage of the project when date for completion is over. Ruth can sue the contractor for the delay of the project. The contractor may consequently pay an interest for the delay of the project to Ruth.