Answer :
Answer:
$156 million
Explanation:
The computation of the value of the project is shown below:
Value of the Project = Present Value of Incremental cash Inflows - Upfront Cost
where,
Present Value of Incremental cash Inflows equals to
= (Incremental Cash inflows) ÷ (Discount rate - Growth rate)
= ($50 million) ÷ (12% - 3%)
= ($50 million) ÷ (9%)
= $556 million
Now the value of the project is
= $556 million - $400 million
= $156 million