In the PDM method activities cannot be started before immediate predecessors are completed A. activities can be repeated B. activities can be started when immediate predecessors are only partially completed C. more flexibility is afforded over usual finish-to-start

Answer :

Answer:

(B) Activities can be started when immediate predecessors are only partially completed.

Explanation:

Precedence diagram method (PDM) is a visual representation technique that depicts the activities involved in a project. It is a method of constructing a project and connects them with arrows that show the dependencies. This method shows the dependencies of one step from their predecessors.