Answer :
Answer:
(B) Activities can be started when immediate predecessors are only partially completed.
Explanation:
Precedence diagram method (PDM) is a visual representation technique that depicts the activities involved in a project. It is a method of constructing a project and connects them with arrows that show the dependencies. This method shows the dependencies of one step from their predecessors.