Answer :
Answer:
b. $4.00 per labor-hour
Explanation:
The computation of the predetermined overhead rate is shown below:
Predetermined overhead rate = Estimated overhead ÷ Estimated labor hours
= $300,000 ÷ 75,000 labor hours
= $4.00 per hour
By dividing the estimated overhead by the estimated labor hours we can find out the predetermined overhead rate and we did the same in the above calculation