What is the first step in developing a project scope management plan? a. Identify stakeholders. b. Create a Work Breakdown Structure. c. Create a project Scope Statement. d. Collect requirements.

Answer :

fichoh

Answer: C. Create a project scope statement

Explanation: A project scope statement is the first step to be taken in creating a project scope management plan. The project scope statement is usually used to highlight the major overview of a project which should include what the project is aimed at or simply put the project objectives, what to expect from the project, that is, the deliverables, the project requirement and constraint. The project scope statement is used to ascertain and establish the what deliverables or expectations are within the confines of the project.