Answer :
Answer:
$115,000
Explanation:
Calculation for the total expected cost
First step is to find the variable cost per unit
Variable costs per unit= 60,000/40,000
Variable costs per unit= 1.50 per unit.
Second step is to find the Total variable costs
Total variable costs =50,000 units × 1.50 per units
Total variable costs=$75,000
Last step is add the total fixed costs of the amount of $40,000 to the Total variable costs of $75,000
Total expected cost =$75,000+$40,000
Total expected cost =$115,000
Therefore the total expected cost will be $115,000