Vertis Corporation is interested in cutting the amount of time between when a customer places an order and when the order is completed. Details for the first quarter of the year are provided here. Choose the correct answer from the options provided. Days Wait time 14 Inspection time 0.6 Process time 5 Move time 0.4 Queue time 6 What is the throughput time

Answer :

Answer:

12

Explanation:

Computation for throughput time

Using this formula

Throughput time = Process time + Inspection time + Move time + Queue time

Let plug in the formula

Throughput time=5+0.6+0.4+6

Throughput time=12

Therefore the Throughput time will be 12