45 people in a certain company can work together to finish a project in 15 days. For a project of the same workload, the
company decided to use 15 people. Assume all people have the same level of productivity.
In how many days can this project be completed?
SELECT ONLY ONE
5 days
10 days
22.5 days
45 days

Answer :

Given:

45 people will accomplish the given task in 15 days.

To find:

Days taken by 15 people to complete the same task.

Solution:

Since, 45 people of a company can finish a work in 15 days

Therefore, 1 person can accomplish the task in days = [tex]15\times45[/tex]

                                                                                        = [tex]675[/tex] days

15 people will accomplish the same task in number of days = [tex]\frac{675}{15}[/tex]

                                                                                                    = [tex]45[/tex]

Therefore, number of days taken by 15 people to accomplish the same task will be 45 days.