Following the question above (Network Diagram) As a project manager, you are responsible for a new facility development project. days. The project is finished once activity H is completed. What is the critical path? A→B→D→F→G→H
A>C>D>F→G→H
A→C>E>F→G→H
A→B>E>F→G→H
A>C>D>G→H