"the time to complete a project is inversely proportional to the number of people who are working on the project. a class project can be completed by 6 students in 24 days. in order to finish the project in 6 days, how many more students should the group add"

Answer :

lalax
6students-->24days
6x4 students--> 6days
24students-6students= 18students